Wednesday 18 February 2009

Day 38 - Bathroom and Clear Out


Today the plumbers and builders worked together to fit the units into the bathroom and access hole to the floor so that we can reach one of the mascerators if needed.  The other mascerator required the carcasses of the fitted units to be butchered.  The plumbers will be back tomorrow to finish off and Marcus and Simon cleared out all their stuff from the loft and the garage and the scaffolding, with the exception of the circular saw and nail gun which will be needed when they pop back to finish off the skirting in the bathroom when the plumbers are done.   Only one problem - when they cut the panel for under the basin, the manufacturer's template was followed - but it was wrong.  So David picked up a new panel and that will be fitted when Marcus comes back.

No comments: