Day 16 - Structure Complete



The day started with a hasty meeting about the bathroom.  Having spent most of the night considering our options we delivered our verdict to the plumbers, who straight away got down to moving the pipes they had already laid for the basin and shower.  They were also able to complete the macerator discharge pipe now, which luckily didn't have to change (because they hadn't done that end of it yet).  Then they came inside and connected up all the pipes in the airing cupboard.
Meanwhile, Marcus and Simon carried on with the remainder of the structural work.  They completed the dwarf wall on top of the steel beam which will become the wall of the stairwell.  They removed the purlin from above the stairs, where it will be in the way, and trimmed the joists for the last Velux window.  They also installed a big chunk of timber to support the end of the front ridge beam.
By 15:30 they were taking bags of rubbish to the skip, so we got a quick progress update.  The structure is now all complete, so the building inspector will be coming to inspect it tomorrow.
The next phase is electrical first fix before the chicken-wire goes down with insulation on top.  The evening was spent finalising where the sockets and lights are going to go.

Thursday, 15 January 2009

We Have a Problem

Steve the plumber mentioned it first. As he measured up for where the pipes had to go, he said we were a bit tight between the wash basin and the shower. There wouldn't be room to stand in front of the basin, let alone bend over to wash your face.
We checked our plans and realised that we had drawn the wash basin smaller than it really is. So it was our planning error. And something has to be done about it - the bathroom will be unusable if we build it as planned. We have a few options:
  • Re-arrange the whole bathroom and put the shower on the opposite wall. This would require a different window (the original has already been ordered).
  • Get a smaller shower (we've already bought the big one).
  • Get a smaller basin - such as a counter-top one.
  • Move the walls to make the bathroom bigger - clearly not a cheap option at this stage.
After a sleepless night and a lot of thinking, we decided to go with a combination of a smaller shower and a minor re-arrangement of the furniture. This will lead to a bit of re-work by the plumbers, and we'll have to sell that big shower enclosure on ebay (what would we do without ebay?) At least now we will have a bathroom that works, even if our shower won't be quite the monster we had been expecting.